Dear neighbors,
I’m writing on behalf of the board to update you about the progress on the common area repairs and refurbishment.
Marina repair:
Randy Gifford of Gifford Island Repair will be beginning the work as early as perhaps this weekend.
Sequencing: Randy plans to start with slip #1-2 and work his way consecutively by number toward the back of SBPOA. As a reminder, here are the 17 docks to be repaired, noted in the board report to the membership on February 13:
Slip # 1/2 Steinmetz/Appel
Slip # 3/4 Buckley
Slip # 5/6 Chamberlin/Buckley
Slip # 7/8 Zinn/Bouchard
Slip # 9/10 Tedesco/Miller
Slip #11/12 McDermond/Taylor
Slip #13/14 Robertson/Aden
Slip #15/16 Gray/Park
Slip #17/18 Willey/Jack Green
Slip #19/20 Buckley/Keyse-Walker
Slip #21/22 Karlene (Lahser)/Gilles
Slip #25/26 Karlene (Lahser)/Zorn
Slip #27/28 Green/Schwandt
Slip #29/30 Lambert/Flint
Slip #31/32 Noonan/Yeomans
Slip #33/34 Marcus/Blank
Slip #41 Hilkene
Materials and work site management: The WearDeck and lumber has been delivered to the Dillman driveway as arranged with Blair, but all construction tools will be located immediately adjacent to each dock being worked on on a particular day.
Mike Aden and the Dave and Michele Zinn have approved locating the dumpster in their driveway. It will be delivered today, probably.
Barring weather interference or other unforeseen problems, Randy thinks the job will take 8-10 days. Work will not begin before 8:00 a.m. during the project.
Sod replacement:
Sod has been ordered to replace areas of damaged grass along the marina. We do not yet have a start-date for that work from Mike Jendrusiak.
Road recapping:
This work has not yet been scheduled, pending a bid for the job, but obviously it won’t be scheduled until the other two projects mentioned above are completed.
Please let the board know if you have any questions or concerns at seagullbaysecretary@gmail.com.
Best wishes,
Your Board of Directors